An input to Close Project or Phase is:
An input to Close Project or Phase is:
Which type of diagram includes groups of information and shows relationships between factors, causes, and obje
Which type of diagram includes groups of information and shows relationships between factors,
causes, and objectives?
An output of the Direct and Manage Project Work process is:
An output of the Direct and Manage Project Work process is:
Activity cost estimates are quantitative assessments of the probable costs required to:
Activity cost estimates are quantitative assessments of the probable costs required to:
External organizations that have a special relationship with the enterprise and provide specialized expertise
External organizations that have a special relationship with the enterprise and provide specialized
expertise are called:
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is c
The item that provides more detailed descriptions of the components in the work breakdown
structure (WB5) is called a WBS:
Which process involves subdividing project deliverables and project work into smaller, more manageable portion
Which process involves subdividing project deliverables and project work into smaller, more
manageable portions?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid
How should a stakeholder who is classified as high power and low interest be grouped in a
power/interest grid during stakeholder analysis?
In a project, total float measures the:
In a project, total float measures the:
What was the original budget at completion for the project?
The project has a current cost performance index of 0.80. Assuming this performance wi continue,
the new estimate at completion is $1000. What was the original budget at completion for the
project?