Which process in Project Time Management includes reserve analysis as a tool or technique?
Which process in Project Time Management includes reserve analysis as a tool or technique?
what is the expected duration of the activity?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule
activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated
to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by
Which risk management strategy seeks to eliminate the uncertainty associated with a particular
upside risk by ensuring that the opportunity is realized?
What is the primary benefit of meeting quality requirements?
What is the primary benefit of meeting quality requirements?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are
Payback period, return on investment, internal rate of return, discounted cash flow, and net
present value are all examples of:
What is a tool to improve team performance?
What is a tool to improve team performance?
which risk management plan component?
The definition of when and how often the risk management processes will be performed
throughout the project life cycle is included in which risk management plan component?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable pe
Which tool within the Perform Quality Control process identifies whether or not a process has a
predictable performance?
which type of total float?
When a backward pass is calculated from a schedule constraint that is later than the early finish
date that has been calculated during a forward pass calculation, this causes which type of total
float?
what is the project CV?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project
CV?