All of the following are tools and techniques that may be used during this process:
During the Develop Schedule process, a Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:
Which of the following is NOT output of Qualitative Risk Analysis ?
Which of the following is NOT output of Qualitative Risk Analysis ?
A project management professional can compare earned value performance data to all of the following project ma
A project management professional can compare earned value performance data to all of the following project management tools EXCEPT:
Reserve Analysis technique is NOT used during __________.
Reserve Analysis technique is NOT used during __________.
Estimate Costs_____________.
Estimate Costs_____________.
What is the standard deviation for the estimates?
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. What is the standard deviation for the estimates?
The final price (your total reimbursement) is _________.
The seller delivers a fixed price plus incentive fee project at a cost of $90,000. The terms of the contract are a ceiling price of $120,000, a target cost of $ 100,000, a target profit of $10,000, and a target price of $110,000. The share ratio is 70/30. The final price (your total reimbursement) is _________.
Which of the following Enterprise Environmental factors are not the inputs for the Develop Human Resource Plan
Which of the following Enterprise Environmental factors are not the inputs for the Develop Human Resource Plan process:
The plan should then be reviewed for the __________.
To shorten project duration, resources have been added to tasks on the critical path. The plan should then be reviewed for the __________.
The review of key deliverables and project performance at the conclusion of a project phase is called:
The review of key deliverables and project performance at the conclusion of a project phase is called: