If a project manager is using observation and conversation to help control the project, she must be involved i
If a project manager is using observation and conversation to help control the project, she must be involved in which process?
Which of the following would be the MOST appropriate thing to do during the planning process group?
Which of the following would be the MOST appropriate thing to do during the planning process group?
Which of the following would be the MOST appropriate thing to do during the monitoring and controlling process
Which of the following would be the MOST appropriate thing to do during the monitoring and controlling process group?
This is an example of:
The widget production project is well underway. The requirements are clear that each widget must weigh between 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of the widgets inspected, 47 percent fell within the acceptable weight range. This is an example of:
In which of the following contract types does the buyer have the most cost risk?
In which of the following contract types does the buyer have the most cost risk?
It would be BEST for the project manager to be in what part of the project management process?
A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process?
Which part of the quality management process is the project manager involved in?
During project executing, a project team member informs the project manager that a work package has not met the quality metric, and that she believes it is not possible to meet it. The project manager meets with all parties concerned to analyze the situation. Which part of the quality management process is the project manager involved in?
What is the BEST thing to do?
The project manager notices that project activities being completed by one department are all taking slightly longer than planned. To date, none of the activities/work packages have been on the critical path, nor have they affected the critical chain planning that has occurred. The project manager is bothered by the problem, since four of the next five critical path activities are being completed by this department. After making three calls, the project manager is finally able to converse with the department manager to determine what is going on. The conversation is slow, because both speak different native languages and they are trying to converse in French, a shared language. To make communication easier, the project manager frequently asks the department manager to repeat back what has been said. The department manager communicates that his staff is following a company policy that requires two levels of testing. During the conversation, the department manager also makes a comment that leads the project manager to believe that the policy may include excessive work. This is the fourth time the project manager has heard such a comment. What is the BEST thing to do?
The project manager explains to the sponsor that extra profits should NOT be a worry on this project because:
The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this project because:
Which of the following is the LEAST effective way to influence the factors that create changes to the cost bas
Which of the following is the LEAST effective way to influence the factors that create changes to the cost baseline?