DRAG DROP
Click the Task button.

A customer is using Global Workload Manager to manage Instant Capacity and Temporary Instant
Capacity processor resources in two nPartitions in a complex. The Production nPartition has an
Own Borrow policy.
For this scenario, use drag and drop to place the panels in the correct order that Global Workload
Manager will activate and deactivate resources. The initial state of the system is shown in the task
and the Production nPartition is starting a long running process that requires four processors. The
load on the Dev and Test nPartition is subsiding at the same time.

PrepAway - Latest Free Exam Questions & Answers

Answer: