How can the administrator fix the configuration?

Refer to the exhibit.

A network administrator sends the cURL command shown in the exhibit to an HP VAN SDN Controller
team in order to add a region to that team. The addresses are as follows:
The team IP address is 192.168.56.10.
The team members IP addresses are 192.168.56.14, 192.168.56.15, and 192.168.56.16.
The administrator receives an error in response. How can the administrator fix the configuration?

How does the team handle this situation?

An HP Comware switch is controlled by a team of HP VAN SDN Controllers. The controllers have these
roles within the region that contains the switch.
Controller 1 = Master
Controller 2 Primary slave
Controller 3 =Secondary slave
A failed network connection causes Controller 1 to lose contact with the switch. Controller 2 and Controller
3 can still reach all the controlled devices. Controller 1 is still up and has contact with other controllers and
switches. How does the team handle this situation?

Which additional component is needed to meet the company’s requirements?

A company is deploying the HP Network Protector SDN Application. The network administrators should be
able to see information about user identity in the Network Protector interface and logs. The log should
provide the name of the user on that endpoint.
Which additional component is needed to meet the company’s requirements?

What should the administrator do to accomplish this?

Refer to the exhibits on the Exhibit 1 and Exhibit 2 tabs.
Exhibit 1

Exhibit 2

Three HP switches are controlled by an HP VAN SDN Controller. The exhibits show the topology that the
controller has discovered for the switches and the port status on the 192.168.0.252 switch. All the
interswitch links carry the same VLANs.
The 192.168.0.249 switch and the 192.168.0.252 switch also connect on a link that is not shown in the
topology. The network administrator wants to make all of the links between the switches available for SDN
applications to use. What should the administrator do to accomplish this?

What must the network administrator do on interface Ten-GigabitEthernet 1/0/2 to enable this behavior?

Refer to the exhibits.
Exhibit 1

Exhibit 2

The switch and server will transmit Fibre Channel over Ethernet (FCoE) traffic on the Ethernet link. If
congestion occurs, the devices should pause the FCoE transmissions rather than drop them. What must
the network administrator do on interface Ten-GigabitEthernet 1/0/2 to enable this behavior?