PrepAway - Latest Free Exam Questions & Answers

What must be done to achieve this?

An organization builds a new datacenter containing vSphere clusters and a new vCenter
Server. The organization needs to add a new vCD cell to the existing architecture. What
must be done to achieve this?

PrepAway - Latest Free Exam Questions & Answers

A.
Complete the configuration of vCloud Director and vShield Manager at the new
datacenter.

B.
Attach the new vCenter Server from the Administration tab in the vCloud Director GUI.

C.
Enable linked mode for the vCenter Servers, then register the new vCenter Server with
the existing vCloud Director and vShield Manager.

D.
Complete the configuration of vCloud Director at the new datacenter and enable linked
mode fpr the vCenter Servers.

Explanation:


Leave a Reply