Which of these activities are essential to achieving the objective of Phase F?

1.F.1: Which of these activities are essential to achieving the objective of Phase F?

A.
Consider implementation sequencing based on business drivers and constraints.

B.
To sort the implementation projects into priority order for implementation and migration.

C.
Assessing the dependencies between work packages.

D.
Assess the costs and benefits of the various implementation projects.

E.
All of these