Scenario Turbonix Enterprises Please read this scenario prior to answering the question
Turbonix Enterprises specializes in the development of wind turbine blades for use in
large-scale commercial wind energy production systems. Turbonix has manufacturing
facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Manitoba .
Each of these plants supplies a different manufacturer that builds and sells complete
systems. The turbine blades are custom engineered to meet each manufacturer’s design
specifications. Until recently, most turbine blades were fabricated manually using molded
fiber-reinforced plastics. However, recent improvements in composite materials, coupled
with enhanced automated methods for precision application of materials during the molding
process, have led to significant reduction in weight, increase in strength, and greatly
improved blade longevity. Turbonix has pioneered the development of a proprietary
automated process for continuous extrusion of the turbine blades. Patents have been filed
to protect the process, but certain trade secrets must be closely guarded. Turbonix has a
mature Enterprise Architecture organization that is supported by a cross-functional
Architecture Review Board. The Chief Information Officer and the Chief Operating Officer
cosponsor the Enterprise Architecture program. Turbonix has used T06AF and its
Architecture Development Method (ADM) to develop its automated manufacturing
processes and systems that are used to design, manufacture, and test the blade
assemblies. They have adapted their Enterprise Architecture to closely follow the TOGAF 9

framework. All of Turbonix’s enterprise architects have been trained and certified on TOGAF
9.Recently, an architecture project was completed that defined a standard approach for
controlling the Automated Test System that is used at each plant to perform final quality
assurance tests on each completed blade assembly. The Manufacturing Architecture Board
approved the plan for immediate implementation at each plant. An Architecture Contract
was developed that detailed the work needed to implement and deploy the new Automated
Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern
that a uniform process be employed at each site to ensure consistency. Refer to the
Turbonix Enterprises Scenario You are the Lead Architect for this activity. You have been
asked to recommend the best approach to adopt to address the Chief Engineer’s concern.
Based on TOGAF 9, which of the following is the best answer?