Refer to the exhibit.
Traffic going from Corp-A-DC-2 towards Corp-B will always use Link-1. Traffic from Corp-B back to Corp-A-DC-
1 may traverse Corp-A-DC-1, over the GigaMAN before it reaches Corp-A-DC-2. No TCP connections are
initiated from Corp-B to either Corp-A-DC-1 or Corp-A-DC-2. Unfortunately, the customer does not have any
money to purchase any additional Steelheads. What are some possible fixes to ensure optimization occurs
while Link-1 is operational? (If Link-1 ceases to function, optimization is not possible.) (Select 2)
A.
Configure a fixed-target rule on the Corp-A-DC-2 Steelhead pointing to the Corp-B Steelhead on port 7800
B.
On the Corp-B Steelhead, enable “in-path probe direct”
C.
On the Corp-A-DC-2 Steelhead, enable “in-path probe direct”
D.
Configure the Corp-A-DC-2 Steelhead to inject a route into the network
E.
Enable Full Transparency