PRINCE2 Exam Questions

Which product would the Project Manager use for gathering Work Package progress information?

Which product would the Project Manager use for gathering Work Package progress information?

A.
Highlight Report

B.
Daily Log

C.
Checkpoint Report

D.
Product Status Account