PRINCE2 Exam Questions

which product should be updated to reflect this?

If, at the end of each stage, circumstances external to the project had changed which affect the
project’s costs, risks and benefits, which product should be updated to reflect this?

A.
Exception Plan

B.
Project Plan

C.
Project Brief

D.
Business Case