Which of the following statements about the Closing a Project process are true?

Which of the following statements about the Closing a Project process are true? 1. The
Closing a Project process provides a fixed point for the receipt of completed Work 2. The
Closing a Project process provides a fixed point to review if the objectives set out in the
original Project Initiation Documentation have been achieved. Packages for the work
performed in the final stage.

A.
Only 1 is true

B.
Only 2 is true

C.
Both 1 and 2 are true

D.
Neither 1 or 2 are true