PRINCE2 Exam Questions

Which of the following statements about lines of authority and reporting are true?

Which of the following statements about lines of authority and reporting are true? 1. The
Project Manager has day-to-day control for a management stage within the limits laid, 2. If a
Team Manager forecasts a deviation beyond Work Package tolerances, this should be
referred to the Project Manager down by the Project Board.

A.
Only 1 is true

B.
Only 2 is true

C.
Both 1 and 2 are true

D.
Neither 1 or 2 are true

Explanation: