Which of the following statements about lines of authority and reporting are true? 1. The
Project Manager has day-to-day control for a management stage within the limits laid, 2. If a
Team Manager forecasts a deviation beyond Work Package tolerances, this should be
referred to the Project Manager down by the Project Board.
A.
Only 1 is true
B.
Only 2 is true
C.
Both 1 and 2 are true
D.
Neither 1 or 2 are true
Explanation: