Which of the following are typical core activities within configuration management?

Which of the following are typical core activities within configuration management? 1.
Planning 2. Risk assessment 3. Verification and audit 4. Identification

A.
1, 2, 4

B.
1, 3 ,4

C.
1, 2, 3

D.
2, 3, 4