When updating the project plan as part of Managing a stage boundary, what else might be updated?
A. Exception Plan
B. Project Management team
C. Business Case
D. Project Initiation Documentation
4 Comments on “what else might be updated?”
networkmanagers says:
I choose A
0
1
Jamalsays:
A is not correct, it is wrong! Exception plan is something which can be created in the MB process…Make sure you know the difference between updating and creating.
I choose A
0
1
A is not correct, it is wrong! Exception plan is something which can be created in the MB process…Make sure you know the difference between updating and creating.
Correct answer must be C!
1
0
yes
0
0
c!
0
0