which statement about the Configuration Management Strategy for the Outsourcing project is correct?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH’s
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
According to PRINCE2, which statement about the Configuration Management Strategy for the
Outsourcing project is correct?

which statement about appointing the MFH Quality Manager to administer the configuration management procedure

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH’s
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
According to PRINCE2, which statement about appointing the MFH Quality Manager to administer
the configuration management procedure is correct?

\Nhat is the next action the Project Manager should consider?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH’s
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
Having created the Issue Report and analyzed the impact of removing the Facilities Division from
the scope of the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next
action the Project Manager should consider?

What products will be impacted by this change?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH’s
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
What products will be impacted by this change?

What additional risk will this place on the project?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH’s
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
What additional risk will this place on the project?

What will be the impact on the benefits?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH’s
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
What will be the impact on the benefits?