Which two tasks should be completed as part of the post-implementation phase of a project?

Which two tasks should be completed as part of the post-implementation phase of a project?
(Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
update the Build Guide

B.
leave your contact number

C.
set aside time to conduct training and transfer of Information

D.
clean up the configuration and let the customer build the configuration afresh