When sizing high-availability workloads, how should you plan for failover performance?
A.
size high-availability workloads so performance remains the same even when only one controller is operational as during normal operation
B.
size high-availability workloads with the expectation there is some degree of performance degradation when only one controller is operational
C.
size high-availability workloads so performance meets the customer’s expectations when there is failover and only one controller is
operational
D.
size high-availability workloads with the understanding there is not a way to adjust for performance degradation when only one controller is
operational
I agree with the answer. C
0