You need to select a FIM topology that meets the following requirements: Removes single points of failure

You are planning to deploy Forefront Identity Manager (FIM) 2010 in your company network. You need to select
a FIM topology that meets the following requirements: Removes single points of failure. Separates end-user
operations from administrative data synchronization. What should you do? (Choose all that apply.)

PrepAway - Latest Free Exam Questions & Answers

A.
Create two service partitions.

B.
Create four service partitions.

C.
Create two instances of the FIM Service by using two FIM Service Names.

D.
Create four instances of the FIM Service by usingtwo FIM Service Names.