You need to generate an earned value report that fulfills management’s requirements

You need to generate an earned value report that fulfills management’s requirements. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Configure a Project Detail view with earned value fields.

B.
Configure a Project Center view with earned value fields.

C.
In Microsoft Office Project Professional 2007, create a visual report.

D.
In Microsoft Office Project Professional 2007, display the Earned Value table.