Microsoft Exam Questions

You need to ensure that the ACWP shows data other than $0

You measure the performance of a project you are tracking in Microsoft Office Project Standard 2007 by updating the completion percentage of the tasks. The actual cost of work performed (ACWP) for all tasks is $0.00. The project has a baseline and all values have been calculated. You need to ensure that the ACWP shows data other than $0.00. What should you do first?

A.
Assign budget resources to the project summary task.

B.
Enter standard resource rates that are greater than zero.

C.
Select the Manual calculation mode, and then perform a calculation.

D.
Select the Physical % Complete option for earned value purposes.