In Microsoft Office Project Standard 2007, you are viewing a project plan in the default Gantt Chart view. You need to create a summary task from an Outline Level 1 task. What should you do?
A.
Set the Outline Level 1 task as a milestone.
B.
Indent the subtasks that appear below the intended summary task.
C.
Create start-to-start dependencies between the summary task and the subtasks.
D.
Edit the Work Breakdown Structure (WBS) code to remove all but the first-level code.