You need to create a project plan that accommodates the corporate holiday calendar. What
should you do?
A.
Add exceptions to the project calendar for corporate holidays.
B.
Create an interim plan that includes the defined holidays to track the holidays.
C.
Create a task for each holiday and assign each resource to each holiday task.
D.
Adjust the maximum units for each resource to reflect the total working days for the year.
Explanation: