You need to apply the upgrades from the staging environment to the production environment

Your company has a System Center 2012 infrastructure. The infrastructure contains the App
Controller and Virtual Machine Manager (VMM) roles. You deploy a service named SRV1 to the
production environment in the public cloud. You also deploy SRV1 to a staging environment in the
public cloud. You perform upgrades to SRV1 in the staging environment. You need to apply the
upgrades from the staging environment to the production environment. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
From the VMM Administrator Console, create a new service template.

B.
From the VMM Administrator Console, create a new virtual machine template.

C.
From the App Controller portal, import an SSL certificate.

D.
From the App Controller portal, perform an environment swap upgrade.

E.
From the VMM Administrator Console, create a new service.

Explanation:
http://technet.microsoft.com/en-us/library/hh221342.aspx
Public cloud services can be upgraded in one of two ways: an environment swap or an in- place
upgrade. An environment swap places the staging environment into the production environment. As
the swap occurs, the existing production environment is moved into the staging environment. An inplace upgrade replaces the existing binaries and settings with new binaries and settings.