You have several bills of materials (BOMs) that include an item manufactured by a third
party. The third party plans to discontinue the production of the item. You need to locate all
of the BOMs that include the item. Which report should you use?
A.
Order lines
B.
Where-used
C.
Calculation
D.
On-hand inventory
Explanation: