Which warehouse will be used for the component line?
When adding a component line to a bill of materials (BOM), you discover that the Resource
consumption check box is cleared and a warehouse is not specified. Which warehouse will
be used for the component line?
Which three types of information should you identify?
You need to identify which type of information you can obtain by performing bill of materials
(BOM) calculations? Which three types of information should you identify? Each correct
answer presents part of the solution.
What should you identify?
You need to identify what happens to the on-hand inventory of a bill of materials (BOM) and
the components of the BOM when you report a BOM as finished. What should you identify?
What should you identify?
You plan to start using product change cases. You need to identify what must be configured
before you can create a new product change case. What should you identify?
Which three options can be used to create a new version of the BOM?
You need to create a new version of a bill of materials (BOM). Which three options can be
used to create a new version of the BOM? Each correct answer presents part of the
solution.
What should you identify?
You need to identify what information is available in the Composed of – tree form from a
sales order line. What should you identify?
Which statement about these configurations is true?
You create a new product and a new bill of materials (BOM) for the product. The product is
available in three different configurations. Which statement about these configurations is
true?
what does the Vendor line type indicate?
You create a new product that has a bill of materials (BOM). You add several lines to the
BOM. Some of the lines are items. Some of the lines represent a sub-assembly. You set the
line type for one of the sub-assembly lines to Vendor. In this situation, what does the
Vendor line type indicate?
Which cost should you identify?
You have a bill of materials (BOM) item. All lines of the BOM item use a constant scrap
amount and a variable consumption. You identify that when you have a production run of
100 items, the scrap cost is 10 US dollars and the unit cost is one US dollar. You need to
identify what will be the cost in the BOM calculation when you increase the size of
production to 200 units. Which cost should you identify?
What should you configure?
You need to ensure that when users perform bill of materials (BOM) calculations, they
receive a warning message if any manufactured components are missing an active BOM.
What should you configure?