Which of the following actions should you take?

You are employed as an administrator at ABC.com. ABC.com makes use of Microsoft Dynamics
AX 2012 in their production environment.
You have created a Lean Manufacturing production flow model, and must now configure a work
cell. You want to make sure that the input and output warehouse, as well as the location for the
work cell are suitably defined.
Which of the following actions should you take?

PrepAway - Latest Free Exam Questions & Answers

A.
You should consider configuring the ResourceGroup, in the Resources section on the Work
Cell CapacityFastTabof Organization Administration.

B.
You should consider configuring the ResourceGroup, in the Resources section on the Kanban
Schedule tab of ProductionControl.

C.
You should consider configuring the ResourceGroup, in the Resources section on the Setup
tab of ProductionControl.

D.
You should consider configuring the ResourceGroup, in the Resources section on the Common
tab of OrganizationAdministration.

Explanation: