PrepAway - Latest Free Exam Questions & Answers

Which four actions should you perform in sequence?

DRAG DROP
Your company has a datacenter in Los Angeles.
The datacenter contains a System Center 2012 Virtual Machine Manager (VMM) infrastructure.
You install the Microsoft Server Application Virtualization (Server App-V) Sequencer on a server named AppV1.
You need to create a virtual application package for an application named VirtualApp. The solution must ensure
that you can specify custom installation options for VirtualApp.
Which four actions should you perform in sequence? (To answer, move the four appropriate actions from the
list of actions to the answer area and arrange them in the correct order.)
Select and Place:

PrepAway - Latest Free Exam Questions & Answers

Answer:

Explanation:
Note:
Here are the five steps to create a Server App-V package:
Install Server App-V Sequencer
Start Server App-V Sequencer to monitor the system
Launch and install your application
Stop Server App-V Sequencer monitoring the system
Save the Server App-V package
https://technet.microsoft.com/en-us/library/gg703284(v=sc.12).aspx