You are planning to add more features to a SharePoint 2010 farm. Two developers are working independently in
a developer environment; each has created a custom solution with a new feature. You have the following
requirements:
Each new feature that the developers created must share an assembly with an existing feature on the production
farm.
.The new features must be deployed from the developer environment to the production environment.
.The possibility must be minimized that an existing application will be unavailable if the assembly needs to be
redeployed after a bug fix.
.You must use the fewest solutions possible.
You need to create a deployment plan that meets these requirements.
Which approach should you recommend?

PrepAway - Latest Free Exam Questions & Answers

A.
Create one solution that combines the two new features with the existing feature and deploy the solution to the production farm.

B.
Create two solutions to deploy the new features and extend the existing solution in the production farm to include the new features.

C.
Create a solution for each of the two new features and extend one of the new solutions to include the feature in the other new solution.
Then deploy both solutions to the production farm.

D.
Create three independent solutions, each consisting of one feature and deploy them separately to the production farm.