what feature would you have the project team use?

You are the project manager of the HHQ Project for your company. You are using the timesheets
feature of Microsoft Project Server and Project Web Access so that team members can complete the
hours spent on their project work. This information is compiled and is used for project billing to the
customer. You have another project, however, that is a fixed fee contract and you would not need to
keep track of hours spent on each task in the project. If you wanted team members to report their
percentage completion of assignments for project scheduling,
what feature would you have the project team use?

PrepAway - Latest Free Exam Questions & Answers

A.
My tasks

B.
My timesheets

C.
My projects

D.
My assignments

Explanation:
The My tasks page allows project team members to send project managers and other roles
information about the percentage of their tasks they have completed.
Answer option B is incorrect. My timesheets is a page where project team members report the
amount of time they have spent on a particular assignment.
Answer option D is incorrect. My assignments is a view that shows what work has been assigned to
an individual – usually a project team member.
Answer option C is incorrect. This is not a valid view for entering time percentage completion
information.