You are consultant who works for Contoso, Ltd. You are implementing Microsoft Dynamics 365 for Finance and Ope

You are consultant who works for Contoso, Ltd. You are implementing Microsoft Dynamics 365 for Finance and Operations and have gathered requirements from the client for their budgeting process.

You

need to identify which requirements from Contoso, Ltd. should be configured as a budget planning stage.

Which requirement should you identify?

A. The budget plan needs to use a workflow that routes for two approvals before the status can

change to

approved.

B. The budget plan needs to go through three steps for created, approved, and final.

C. The budget plan needs to include prior year actual and prior year budget quantities and amounts.

D. The budget plan needs to include two objectives; one fo

r lower cost and another for increasing sales.

References: