Microsoft Exam Questions

How should you assign the resources?

You are developing a project schedule in Microsoft Office Project Standard 2007. You create a fixed units, effort-driven task that has a duration of 10 days. You will assign two resources to the task. Each resource works 8 hours per day. You need to divide the 160 hours of effort evenly between the resources. How should you assign the resources?

A.
Individually, accepting the default values.

B.
Individually, entering a Units value of 50%.

C.
Simultaneously, accepting the default values.

D.
Simultaneously, entering a Units value of 50%.