How many scheduled jobs should you create from Windows Backup?

You have a file server named Server1 that runs Windows Server 2003 Service Pack 2 (SP2).

You need to use Windows Backup to meet the following requirements:
Minimize the number of scheduled backup jobs.
Perform a scheduled normal backup to disk every Friday.
Perform a scheduled normal backup to tape every Friday.
Perform scheduled differential backups to tape every Monday, Tuesday, Wednesday, and Thursday.

How many scheduled jobs should you create from Windows Backup?

PrepAway - Latest Free Exam Questions & Answers

A.
one

B.
two

C.
three

D.
six