Which command should you run next?

You have the Windows Assessment and Deployment Kit (Windows ADK) installed.
You create a Windows Preinstallation Environment (Windows PE) image.
While resting the deployment of the Windows PE image, you discover that the Windows PE installation
becomes unresponsive. You discover that you are exceeding the memory capacity of the RAM disk.
You need to increase the memory capacity of the RAM disk used by the Windows PE image.You mount the Windows PE image.
Which command should you run next?

What should you identify?

DRAG DROP
You are preparing a GTP disk for a Unified Extensible Firmware Interface (EUFI)-based computer from
Windows Preinstallation Environment (Windows PE).
You need to identify which file system must be used for the EFI system partition, the MSR partition, and the
Windows partition.
What should you identify? (To answer, drag the appropriate actions to the correct partitions. Each action may
be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view
content.)Select and Place:

Which two requirements should you identify?

Your company plans to implement a deployment environment.
The company identifies the following requirements for the planned implementation:
Install multiple computers simultaneously.
Use the least amount of network traffic to deploy images.
Automatically start the deployment only when 10 computers are ready for installation.
Ensure that all customers accept the End-user License Agreement (Eula) the first time they start their
computer.
A manager at the company recommends deploying generalized images from a network share.
You need to identify which requirements the recommendation meets.
Which two requirements should you identify? Each correct answer presents part of the solution.

Which two requirements should you identify?

A customer plans to deploy Windows Server 2012 Standard to several servers.
The customer identifies the following hardware requirements for the planned deployment:
Must support three volumes in a single mirror without the installation of third-party management software.
Must support NIC teaming without the installation of third-party management software.
Must be able to back up the server data to a tape device.
Must be able to run on an x86 hardware platform.You need to identify which two requirements are met by the planned deployment of Windows Server 2012.
Which two requirements should you identify? Each correct answer presents part of the solution.

Which two actions should you perform?

You have a server named Server1 that runs Windows Server 2012 and has the Windows Deployment Services
server role installed.
You recently removed a third-party DHCP server from the network, and then installed the DHCP Server role on
Server1.
You create a scope on Server1.
You discover that client computers attempting to receive a Windows 10 image fail to connect to Server1.
You verify that the client computers on the network can receive an IP address from Server1.
You need to ensure that the computers attempting to receive an image can connect to Server1.
Which two actions should you perform? Each correct answer presents part of the solution.

You need to ensure that the reference computers start a…

You have several reference computers. The computers are configured to always start from a local hard disk
drive.
You plan to capture the reference computers.
On each reference computer, you connect a USB flash drive (UFD) that contains an installation of Windows
Preinstallation Environment (Windows PE).
You need to ensure that the reference computers start automatically by using Windows PE from the UFD.What should you do?