Which two actions should you perform?
Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today’s data. Which two actions should you perform? Each correct answer presents part of the solution.
What should you do?
You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the problem. What should you do?
Which set of values describes the task?
One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
What should you do?
The red person icon is displayed next to one of your tasks. You need to find out the reason for the display of the icon. What should you do?
What should you do?
You need to ensure that you can view only the tasks on your projects critical path. What should you do?
What percentage of units should be reflected in the schedule by Adam’s workload?
DRAG & DROP
You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish. You update the schedule. What percentage of units should be reflected in the schedule by Adam’s workload?
Which two actions should you perform?
You use Project Professional 2010 to manage a software development project as shown in the exhibit.
You need to cancel the ‘Develop prototype based on functional specifications’ task. You also need to retain all the information from the task. Which two actions should you perform? Each correct answer presents part of the solution.
What should you do?
You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
What should you do?
You need to view Task ID 0 on your project plan. What should you do?
Which command should you use?
You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?