What percentage of units should be reflected in the schedule by Adam’s workload?
DRAG & DROP
You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish. You update the schedule. What percentage of units should be reflected in the schedule by Adam’s workload?
Which two actions should you perform?
You use Project Professional 2010 to manage a software development project as shown in the exhibit.
You need to cancel the ‘Develop prototype based on functional specifications’ task. You also need to retain all the information from the task. Which two actions should you perform? Each correct answer presents part of the solution.
What should you do?
You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
What should you do?
You need to view Task ID 0 on your project plan. What should you do?
Which command should you use?
You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?
What should you do?
What should you do?
You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?
Which two actions should you perform?
The project you manage has only part-time resources. The part-time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? Each correct answer presents part of the solution.
What should you do?
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
What should you modify in the Task Information window?
You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?