Which one of the following estimation approaches is appropriate at this stage of the project?

Topic 10, Scenario 10, V3 “Online Application”
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has proposed an
in-house development with the use of a Rapid Application Development (RAO) approach.
******************************

Which one of the following estimation approaches is appropriate at this stage of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Create an estimate based on the function point analysis technique and test point analysis

B.
Create an estimate based on the complexity of the code

C.
Create an estimate based on the credentials of the successful bidder

D.
Create an estimate based on a percentage of the development effort

Explanation: