To address reliability a number of measures will be taken throughout the development and testing
process. Select TWO appropriate measures that are typically taken as part of reliability engineering and/or testing of an application.

PrepAway - Latest Free Exam Questions & Answers

A.
Define Operational Profiles

B.
State Transition Testing

C.
Usability testing

D.
Perform design FMEAs

E.
Exploratory test

Explanation: