Which of the following are valid reasons for adopting a different life cycle (from the V model), for increment

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
*******************************

Which of the following are valid reasons for adopting a different life cycle (from the V model), for
increments after the first year?
i. We do not have a clear understanding of the requirements from a customer perspective.
ii. We see the risk of delivering requested functionality late as being higher than the risk of
delivering a lower quality product.
iii. We do not have a budget for additional regression testing which is needed to ensure that
existing functionality is not compromised by future iterations.
iv. The company test strategy does not fit well within the V life cycle model.

Which of the following would be the TWO most appropriate examples of entry criteria documented in the system i

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
************************************

Which of the following would be the TWO most appropriate examples of entry criteria documented
in the system integration test plan?

Which of the following is a characteristic of good testing in any life cycle model?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
*******************************

Which of the following is a characteristic of good testing in any life cycle model?

Which test management control option is most appropriate to adopt under these circumstances?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
************************************

Which test management control option is most appropriate to adopt under these circumstances?

Which of the following would you expect to see in the master test plan?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
*******************************

Which of the following would you expect to see in the master test plan?

Which of the following review types would you choose to review the program?

The Bonus Program is perceived by management to be critical. Defects in the program would
almost immediately lead to financial loss. In the past an improvement program has been run to
implement review based on IEEE 1028. Knowledge and skills on both formal and informal reviews
are available. There is also an existing pool of review leaders. Which of the following review types
would you choose to review the program?

which one of the following factors is most likely to lead to a revised view of product risk?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
************************************

Risks should be constantly reviewed. Given the current situation, which one of the following
factors is most likely to lead to a revised view of product risk?

Which of the following would be the most significant input to estimating the time to carry out the specified t

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
*******************************

Which of the following would be the most significant input to estimating the time to carry out the
specified testing tasks?


Page 3 of 7112345...102030...Last »