Topic 7, Scenario 7 “Test Estimation”
You have been contracted to manage the acceptance testing of a new computer-based
reservation system for a travel agency. You have provided an approximate budget estimate for the
testing project based on previous experience with similar sized projects. However, the
management of the parent company of the travel agency will not commit to the budget until
detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the
software are available, as well as an estimate of the total effort that will be spent in developing the
software. The software is to be delivered in four increments, and the functionality to be delivered in
each increment has already been agreed on.
****************************

Identify THREE items that would be part of the work-breakdown structure showing the key testing
activities for the acceptance test project. (for 2 out of 3 correct )

Which aspect in the test estimate is the main risk in this project?

Topic 7, Scenario 7 “Test Estimation”
You have been contracted to manage the acceptance testing of a new computer-based
reservation system for a travel agency. You have provided an approximate budget estimate for the
testing project based on previous experience with similar sized projects. However, the
management of the parent company of the travel agency will not commit to the budget until
detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the
software are available, as well as an estimate of the total effort that will be spent in developing the
software. The software is to be delivered in four increments, and the functionality to be delivered in
each increment has already been agreed on.
******************************

Which aspect in the test estimate is the main risk in this project?

which part of the testing activity is most difficult to estimate?

Topic 7, Scenario 7 “Test Estimation”
You have been contracted to manage the acceptance testing of a new computer-based
reservation system for a travel agency. You have provided an approximate budget estimate for the
testing project based on previous experience with similar sized projects. However, the
management of the parent company of the travel agency will not commit to the budget until
detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the
software are available, as well as an estimate of the total effort that will be spent in developing the
software. The software is to be delivered in four increments, and the functionality to be delivered in
each increment has already been agreed on.
****************************

In general which part of the testing activity is most difficult to estimate?

why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort?

Topic 7, Scenario 7 “Test Estimation”
You have been contracted to manage the acceptance testing of a new computer-based
reservation system for a travel agency. You have provided an approximate budget estimate for the
testing project based on previous experience with similar sized projects. However, the
management of the parent company of the travel agency will not commit to the budget until
detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the
software are available, as well as an estimate of the total effort that will be spent in developing the
software. The software is to be delivered in four increments, and the functionality to be delivered in
each increment has already been agreed on.
****************************

In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of
development effort? Identify THREE valid reasons.

Which one of the following standards do you believe would be most appropriate to take into account for complia

Topic 8, Scenario 8, V2 “Test Proems Improvement’
You have raised the issue that improving the testing process is also dependent on the status of
the software development process.
****************************

The test improvement project will take place in an organization developing a safety-critical
avionics application. Which one of the following standards do you believe would be most
appropriate to take into account for compliance during your assignment?

Which aspect in the test estimate is the main risk in this project?

Topic 7, Scenario 7 “Test Estimation”
You have been contracted to manage the acceptance testing of a new computer-based
reservation system for a travel agency. You have provided an approximate budget estimate for the
testing project based on previous experience with similar sized projects. However, the
management of the parent company of the travel agency will not commit to the budget until
detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the
software are available, as well as an estimate of the total effort that will be spent in developing the
software. The software is to be delivered in four increments, and the functionality to be delivered in
each increment has already been agreed on.
****************************

Which aspect in the test estimate is the main risk in this project?