What is the primary goal of disaster recovery planning (DRP)?

What is the primary goal of disaster recovery planning (DRP)?

A.
Integrity of data

B.
Preservation of business capital

C.
Restoration of business processes

D.
Safety of personnel

Explanation:
Answer D is correct; Loss of human life is the highest impact of any risk; personnel safety is the primary concern of all 10 domains, including business continuity and disaster recovery planning.