All of the following items should be included in a Business Impact Analysis (BIA) questionnaire EXCEPT questions that

A. determine the risk of a business interruption occurring

B. determine the technological dependence of the business processes

C. Identify the operational impacts of a business interruption

D. Identify the financial impacts of a business interruption

Reference: https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&uact=8&ved=0ahUKEwjbktbTp-LaAhVIr48KHZuhB0UQFggmMAA&url=http%3A%2F%2Fwww.oregon.gov%2Fdas%2FProcurement%2FGuiddoc%2FBusImpAnalysQs.doc&usg=AOvVaw1wBxcnLP8ceI_yhv2rsI9h