Which one of the following is NOT an input to the perform quantitative risk analysis process?
There are five inputs to the quantitative risk analysis process. Which one of the following is
NOT an input to the perform quantitative risk analysis process?
What is the likely outcome of creating this type of chart?
Your project has several risks that may cause serious financial impact should they happen.
You have studied the risk events and made some potential risk responses for the risk
events but management wants you to do more. They’d like for you to create some type of a
chart that identified the risk probability and impact with a financial amount for each risk
event. What is the likely outcome of creating this type of chart?
which one of the following is an output of risk monitoring and control?
You are working as a project manager in your organization. You are nearing the final stages
of project execution and looking towards the final risk monitoring and controlling activities.
For your project archives, which one of the following is an output of risk monitoring and
control?
Which of the following DoD directives is referred to as the Defense Automation Resources Management Manual?
Which of the following DoD directives is referred to as the Defense Automation Resources
Management Manual?
Which of the following processes take place in phase 3?
The phase 3 of the Risk Management Framework (RMF) process is known as mitigation
planning. Which of the following processes take place in phase 3? Each correct answer
represents a complete solution. Choose all that apply.
Which of the following statement is most accurate about the limitations of the checklist analysis approach for
Gary is the project manager of his organization. He is managing a project that is similar to a
project his organization completed recently. Gary has decided that he will use the
information from the past project to help him and the project team to identify the risks that
may be present in the project. Management agrees that this checklist approach is ideal and
will save time in the project. Which of the following statement is most accurate about the
limitations of the checklist analysis approach for Gary?
What are the subordinate tasks of the Initiate and Plan IA C&A phase of the DIACAP process?
What are the subordinate tasks of the Initiate and Plan IA C&A phase of the DIACAP
process? Each correct answer represents a complete solution. Choose all that apply.
What are the different categories of risk?
Information risk management (IRM) is the process of identifying and assessing risk,
reducing it to an acceptable level, and implementing the right mechanisms to maintain that
level. What are the different categories of risk? Each correct answer represents a complete
solution. Choose all that apply.
What will be Neil’s reply to Tom?
Neil works as a project manager for SoftTech Inc. He is working with Tom, the COO of his
company, on several risks within the project. Tom understands that through qualitative
analysis Neil has identified many risks in the project. Tom’s concern, however, is that the
priority list of these risk events are sorted in “high-risk,” “moderate-risk,” and “low-risk” as
conditions apply within the project. Tom wants to know that is there any other objective on
which Neil can make the priority list for project risks. What will be Neil’s reply to Tom?