What should Walter also update in this scenario considering the risk event?

Walter is the project manager of a large construction project. He’ll be working with several vendors
on the project. Vendors will be providing materials and labor for several parts of the project. Some
of the works in the project are very dangerous so Walter has implemented safety requirements for
all of the vendors and his own project team. Stakeholders for the project have added new
requirements, which have caused new risks in the project. A vendor has identified a new risk that
could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the
risk register and created potential risk responses to mitigate the risk. What should Walter also
update in this scenario considering the risk event?

What project management component is responsible for evaluating a change request and its impact on all of the

You are the project manager of the GHT project. This project will last for 18 months and has a
project budget of $567,000. Robert, one of your stakeholders, has introduced a scope change
request that will likely have an impact on the project costs and schedule. Robert assures you that
he will pay for the extra time and costs associated with the risk event. You have identified that
change request may also affect other areas of the project other than just time and cost. What
project management component is responsible for evaluating a change request and its impact on
all of the project management knowledge areas?

what is the risk exposure of the event that must be considered for the cost of the risk response?

You are the project manager of the KJH Project and are working with your project team to plan the
risk responses. Consider that your project has a budget of $500,000 and is expected to last six
months. Within the KJH Project you have identified a risk event that has a probability of .70 and
has a cost impact of $350,000. When it comes to creating a risk response for this event what is the
risk exposure of the
event that must be considered for the cost of the risk response?

What should you do with this verbal demand for a change in the project?

Jane, the Director of Sales, contacts you and demands that you add a new feature to the software
your project team is creating for the organization. In the meeting she tells you how important the
scope change would be. You explain to her that the software is almost finished and adding a

change now could cause the deliverable to be late, cost additional funds, and would probably
introduce new risks to the project. Jane stands up and says to you, “I am the Director of Sales and
this change will happen in the project.” And then she leaves the room. What should you do with
this verbal demand for a change in the project?