What also should the project manager update based on these scope changes?

Your project change control board has approved several scope changes that will drastically alter
your project plan. You and the project team set about updating the project scope, the WBS, the
WBS dictionary, the activity list, and the project network diagram. There are also some changes
caused to the project risks, communication, and vendors. What also should the project manager
update based on these scope changes?

What component of the change control system communicates the approval or denial of a proposed change request?

Thomas is a key stakeholder in your project. Thomas has requested several changes to the
project scope for the project you are managing.
Upon review of the proposed changes, you have discovered that these new requirements are
laden with risks and you recommend to the change control board that the changes be excluded
from the project scope. The change control board agrees with you. What component of the change
control system communicates the approval or denial of a proposed change request?