Which two steps must be carried out to move the DataStage objects to the Production system?

You are describing to your customer how to work with packages. There are two steps that must be
carried out in order to move the package to a target project. Which two steps must be carried out
to move the DataStage objects to the Production system? (Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Build

B.
Export

C.
Deploy

D.
Package

E.
Compile

Explanation: