If vOriginalDate = July 27, and you require vNewDate = Jul2012, which syntax is appropriate to
complete this task?
A.
vNewDate=SUBST(vOriginalDate,3,3) | ‘2012’;
B.
vNewDate=SUBST(vOriginalDate,3,3) & ‘2012’;
C.
vOriginalDate=SUBST(vNewDate,3,3) & ‘2012’;
D.
vNewDate=SUBST(vOriginalDate,3,3) + ‘2012’;
Explanation: