Which action will accomplish the goal?

An administrator has configured a POWER7 server with 6 partitions. The partitions are configured
with shared processor pools and virtual processors as shown:

The IBM i partition configured to use virtual processor capacity indicated in the graphic above as
vp8 is currently shut down, but the administrator needs to reserve the shared processor pool
capacity for use with the IBM i partition once it starts up.

Which action will accomplish the goal?

PrepAway - Latest Free Exam Questions & Answers

A.
De-allocate the entitled capacity from vp8.

B.
Set the uncapped processor weight to 255 (maximum).

C.
Start the IBM i partition into DST, do not start IBM i.

D.
Remove the virtual Partition definition and make vp8 a dedicated processor pool.