Which is not a goal of the Project Planning SMF?

Which is not a goal of the Project Planning SMF?

PrepAway - Latest Free Exam Questions & Answers

A.
Approve all changes to the project

B.
Deliver a clearly scoped project plan

C.
Deliver a functional specification

D.
Produce a master project schedule